Community Diagnostic Centre

Project Outline

PROJECT TYPE: Refurbishment

PROJECT NAME: Community Diagnostic Centre

LOCATION: Florence Nightingale Community Hospital

CLIENT: University Hospitals of Derby and Burton

PRINCIPLE CONTRACTOR: Galliford Try

PROJECT DURATION: 59 weeks

CONTRACT TYPE: NEC3 Option C (ProCure22)

VALUE: £9m

PROJECT STATUS: Complete 2024

Project Description

The New CDC will support the ambitions of Joined Up Care Derbyshire ICS across different organisations and settings in Derby City and Derbyshire, to provide more convenient and personalised care for their health and wellbeing. 

The development of the Florence Nightingale Community Hospital  CDC will support and enhance the clinical pathways that are currently on offer to those communities and the increase in diagnostic activity will help drive improved outcomes in cancer, stroke, heart disease, respiratory diseases, and other conditions, in line with the NHS Long Term Plan commitments. 

Our Role and Key Facts

  • Providing client side NEC3 P22 Project Management
  • Existing hospital basement area, accessed through live hospital
  • 3 phase refurbishment with staged handover
  • Working in a shared office with the PSCP (Galliford Try