New Outpatient Department Extension and Part Refurb

Project Outline

PROJECT TYPE: New build & Refurbishment

PROJECT NAME: New Outpatient Department Extension and Part Refurb

LOCATION: Ridgeway Hospital, Swindon

CLIENT: Circle Health Group

PRINCIPLE CONTRACTOR: PW Group

PROJECT DURATION: 40 weeks

CONTRACT TYPE: JCT D&B

VALUE: £5m

PROJECT STATUS: Complete 2024

Project Description

Single story extension to an existing hospital. The new space provided 9 consult rooms, a spinal operation room and a redeveloped oncology space. In tandem, a new reception was built and a large car park constructed. A busy live site, where works took place in an enclosed courtyard. Planning and management were key. Decants had to be planned and hospital operations were uninterrupted.

Our Role and Key Facts

  • Providing client-side project management and design management supporting the main contractor.
  • Driving value engineering options, such as alternatives to cladding, roof lanterns and automated doors to provide better value for our client and mitigate residual maintenance issues.
  • Managed complex decants of the physiotherapy and oncology department and maintained phased handovers to progressively improve hospital operations.

Client Testimonials

Hear from our satisfied clients and partners

Our Clients and Partners