New Outpatient Department

Project Outline

PROJECT TYPE: New Build & Refurbishment

PROJECT NAME: New Outpatient Department

LOCATION: Priory Hospital Birmingham

CLIENT: Circle Health Group

PRINCIPLE CONTRACTOR: Morgan Sindall

PROJECT DURATION: 36 weeks

CONTRACT TYPE: JCT D&B

VALUE: £3.5m

PROJECT STATUS: Complete 2023

Project Description

Construction of a new outpatient and reception and refurbishment of existing facility to form a new outpatient department for the priory hospital Birmingham. The project consisted of a new steel framed, masonry clad extension and replacement of existing windows and full refurbishment of the existing outpatient department.

Our Role and Key Facts

  • Provided client-side project management
  • Strong management of design and all stakeholders in order to achieve sequential sign off’s at each RIBA stage. Copious last minute client lead design changes have been successfully incorporated and responded to on site. An agile approach has been maintained to suit the nature of our client.
  • Stringent engagement with end users to ensure the space would be fit for purpose and ensure compliance, this was fed back into our design team.